Question: How long must a lot owner wait for a reimbursement for waterproofing the bathroom? What can I do to obtain a resolution?
How long must an owner wait for an entitled and agreed reimbursement for waterproofing the bathroom? What can I do to obtain a resolution?
All invoices were submitted 14 months ago and finally acknowledged. Reimbursement was promised at the AGM 4 months ago, but all to no avail.
Answer: You may consider escalating the matter to the Tribunal.
If the work relates to common property, the Owners Corporation is required to comply with section 106 of the Strata Schemes Management Act 2015.
This section provides that the Owners Corporation must properly maintain and keep in a state of good and serviceable repair the common property and any personal property vested in the Owners Corporation.
You will need to show that the works were necessary to be carried out.
I would suggest you call a meeting at the Annual General Meeting, or at the strata committee meeting (if you are on the strata committee) and/or raise the issue with the strata manager at the first instance. Should this not happen and you can show the works were necessary to be carried out you may then consider escalating the matter to the Tribunal.
This post appears in the March 2021 edition of The NSW Strata Magazine.