Enter your email Address

LookUpStrata

Strata Information Leading to Open Discussion

advert Lannock strata finance
Australia's Top Property Blog Dedicated to Strata Living
  • Home
  • What is strata?
    • Strata Legislation – Rules and ByLaws
    • What is Strata?
    • Glossary of NSW Strata Terms and Jargon
    • Understand Strata Management with this Five-Minute Guide
    • Cracking the Strata Fees Code
    • Strata Finance
  • Strata Topics
    • Strata Information By State
      • New South Wales
      • Queensland
      • Victoria
      • Australian Capital Territory
      • South Australia
      • Tasmania
      • Western Australia
      • Northern Territory
    • Strata Information By Topic
      • By-Laws & Legislation
      • Smoking
      • Parking
      • Noise & Neighbours
      • Insurance
      • Pets
      • Your Levies
      • New Law Reform
      • Maintenance & Common Property
      • Committee Concerns
      • NBN & Telecommunications
      • Building Defects
      • Renting / Selling / Buying Property
      • Strata Managers
      • Building Managers & Caretakers
      • Strata Plan / Strata Inspection Report
      • Apartment Living Sustainability
    • Strata Webinars
      • NSW Strata Webinars
      • QLD Strata Webinars
      • VIC Strata Webinars
      • ACT Strata Webinars
      • SA Strata Webinars
      • WA Strata Webinars
    • Upcoming and FREE Strata Events
  • Blog
    • Newsletter Archives
  • The Strata Magazine
    • The NSW Strata Magazine
    • The QLD Strata Magazine
    • The VIC Strata Magazine
    • The WA Strata Magazine
  • Site Sponsors
  • About Us
    • Testimonials for LookUpStrata
  • Help
    • Ask A Strata Question
    • Q&As – about the LookUpStrata site
    • Sitemap
Home » Defects » Defects NSW » NSW: Is compliance with the DBPA compulsory for a class 2 building in NSW?

NSW: Is compliance with the DBPA compulsory for a class 2 building in NSW?

Published March 27, 2024 By The LookUpStrata Team 2 Comments Last Updated June 26, 2025

Share with your strata community

  • Share
  • LinkedIn
  • Email

A few weeks ago, we conducted a webinar where Sedgwick detailed the tendering process when carrying out remedial work. Below are a few of the questions from our audience that came up during the session, including whether compliance with the DBPA is compulsory.

Table of Contents:

  • QUESTION: An engineer’s scope of work to replace waterproofing membranes includes amounts for insurance and DBPA document lodgement. At this stage of the process, how accurate are the amounts mentioned?
  • QUESTION: Our building complex needs to replace non-compliant balustrades and repair balconies with concrete cancer. Should we repair both issues at the same time? We are concerned about costs and the relevant building regulations.
  • QUESTION: We engaged a registered DBPA Design Practitioner for our remedial building work. However, the qualified building contractors are not DBPA-registered building practitioners. How do we meet DBPA requirements?
  • QUESTION: The DBPA has introduced cost and resource overheads. Is compliance with the DBPA compulsory?

CLICK HERE TO BE NOTIFIED WHEN WE PUBLISH CONTENT TO THE SITE

Question: An engineer’s scope of work to replace waterproofing membranes includes amounts for insurance and DBPA document lodgement. At this stage of the process, how accurate are the amounts mentioned?

Our strata scheme has 33 units in two buildings. The waterproofing membrane on both roofs needs to be replaced. The roofs are a flat concrete structure, and the building was constructed in 1984.

The engineer’s scope of works quoted a $35,000 premium for the HBCF insurance certificate and $20,000 for the lodgement of documents with the DBPA.

How can I check these quotes are reasonable? How do we know the insurance quote is accurate, given we have not yet gone to tender and thus do not have quotes for the repair costs?

Answer: These amounts would likely be subject to change depending on the final project or contract cost.

Costs associated with HBCF and lodgement of documents to comply with the DBPA are generally costs dependent on the extent of works and final value.

If an engineer has prepared a scope, it is unlikely these amounts are fixed quotes and are a guide or provisional allowances that would be subject to change depending on the final project or contract cost.

Check the scope of work qualifications or conditions. If they are unclear, ask the engineer how the costs were established.

Often, provisional allowances are included at the higher end to ensure sufficient funds are allowed. However, the final cost will always be determined once tendering occurs.

Therefore, realistically, checking these costs for accuracy can only occur once the project costs are established. Provisional sums for these items are industry standard, based on the uncertainty of final values.

Bruce McKenzie
Sedgwick
E: [email protected]
P: 1300 735 720

This post appears in the August 2025 edition of The NSW Strata Magazine.

Question: Our building complex needs to replace non-compliant balustrades and repair balconies with concrete cancer. Should we repair both issues at the same time? We are concerned about costs and the relevant building regulations.

We are a Class 2 category building(s) comprising several two-storey townhouses and several three-storey unit blocks built from 1982 to 1984.

Our balustrades are 900mm high and do not meet the current regulations. Some balustrade posts have rusted. An engineer’s report states there is no immediate safety issue, but they need to be fixed. We must replace them with complying balustrades. If we only replace the ones requiring maintenance, the external appearance of the building will be inconsistent.

Can we take the balustrades down, have them repaired and then replace them?

We have some mild concrete cancer in balconies that we also need to repair. Some owners have tiled their balcony, others have not. Some of the tiling was approved, some was not. The engineer found that most, if not all, of the tiled balconies do not have a waterproof membrane. We realised we should have a by-law for improvements to balconies. We are considering lifting the tiles and laying a waterproof membrane.

The engineer advised that the waterproofing is part of an element, including the balcony, sill and doors. The balconies, sills and doors are not compliant. The balconies do not have the right slope, the sills are not high enough, and the doors are not waterproof. Therefore, it seems we would be best to fix all problems at the same time. It will be a costly exercise. Is this the best option?

Answer: One approach worth considering is staging the work over a period of time.

Your questions touch on some complex areas, particularly concerning compliance with the Design and Building Practitioners Act 2020 (DBPA). From what you’ve described, the advice you’ve received from your engineer is likely correct, especially regarding the need to meet current standards when replacing balustrades and addressing issues with the balcony hobs and doors.

These matters are indeed intricate, and as you noted, addressing one element often impacts others — such as how waterproofing, door compliance, and structural integrity must be considered together. The approach recommended by your engineer, which includes replacing non-compliant components and ensuring everything meets current regulations, aligns with best practices under the DBPA.

Given the complexity and potential costs involved, carefully planning these upgrades is crucial. One approach worth considering is staging the work over a period of time. It can help manage the financial impact on owners while meeting all necessary compliance and aesthetic requirements.

David Lamborn
Windowline
E: [email protected]
P: 02 8304 6400

This post appears in the October 2024 edition of The NSW Strata Magazine.

Question: We engaged a registered DBPA Design Practitioner for our remedial building work. However, the qualified building contractors are not DBPA-registered building practitioners. How do we meet DBPA requirements?

Our remedial building work requires NSW DBPA compliance, and we engaged a registered DBPA Design Practitioner. However, the qualified building contractors available are not DBPA-registered building practitioners. What are our options to meet DBPA requirements to submit a building compliance declaration? Can the registered Design Practitioner submit the Building Compliance declaration? Can another builder registered as a Building Practitioner supervise the building contractor doing the work?

Answer: Engage a registered building practitioner who can act as the head contractor or the principal contractor for the building work and oversee the work done by the qualified building contractors.

According to the Building practitioner obligations page on the NSW Fair Trading website, a registered building practitioner must provide a building compliance declaration for the building work, contractor documentation and other required documents within seven days of completing building work. This documentation must be lodged on the NSW Planning Portal and include a statement of variations that did not require a new regulated design. A building compliance declaration cannot be delegated to another person.

Therefore, if the qualified building contractors are not DBPA-registered building practitioners, they cannot submit a building compliance declaration. The registered design practitioner who prepared the regulated designs and design compliance declarations also cannot submit a building compliance declaration, as this is a different role and responsibility under the scheme.

One possible option to meet the DBPA requirements is to engage a registered building practitioner who can act as the head contractor or the principal contractor for the building work and oversee the work done by the qualified building contractors. The registered building practitioner can then submit a building compliance declaration after verifying that the work complies with the declared designs and the Building Code of Australia.

Another possible option is to apply for an exemption from the requirement to provide a building compliance declaration if the building work is considered to be emergency remedial building work. This is defined as building work necessary to prevent or reduce the risk of significant harm or damage to persons or property or to rectify a serious defect in a building element or performance solution. However, this option is subject to the approval of the Secretary of the Department of Customer Service, and may not be granted in all cases.

We hope this helps you understand the options to meet the DBPA requirements for remedial building work. However, please note that this is not legal advice, and you should consult a qualified professional before making any decisions. Also, the information I provided may not be up to date or accurate, as the DBPA scheme is subject to change and interpretation.

Anthony Rahme
Sedgwick
E: [email protected]
P: 0424 750 900

This post appears in the June 2024 edition of The NSW Strata Magazine.

Question: The DBPA has introduced cost and resource overheads. Is compliance with the DBPA compulsory?

We are a small block of eight lots built in the 1980s. We are experiencing waterproofing issues. The Design and Building Practitioners Act 2020 (DBPA) has introduced cost and resource overheads. Is compliance with the DBPA a compulsory tender requirement? Is there a legal obligation, with penalties for non-compliance, to follow the DBPA? Can we remove compliance requirements from our invitations to tender?

CLICK HERE TO BE NOTIFIED WHEN WE PUBLISH CONTENT TO THE SITE

Answer: The primary objective of the Design and Building Practitioners Act 2020 is to protect consumers.

Ultimately, the standard is the standard, and you are required to comply. It is a short-term pain for a long-term gain. While people think it’s onerous and will add cost and time, it must be followed and embraced because the primary objective is protecting consumers.

It may add time and cost to the front end of the project, but it will give you a good outcome in the end. You cannot exclude compliance with the DBPA from a tender. It’s the law for class 2 buildings in NSW.

We have encountered owners who had work done by someone qualified to do a design. However, they were not registered practitioners. The building threw away money because they then had to go back and rework the design with someone who was a registered practitioner. You don’t want to do things twice or three times. You’re much better off doing it right the first time.

Bruce McKenzie & Edwina Feilen
Sedgwick
E: [email protected]
P: 1300 735 720

This post appears in the April 2024 edition of The NSW Strata Magazine.

Have a question or something to add to the article? Leave a comment below.

Read next:

  • NAT: Scope of Work Assisting Committees to Manage Rising Costs
  • NAT: Changing the landscape of consumer protection (Project Intervene)

Visit our Strata Building Defects OR NSW Strata Legislation.

Looking for strata information concerning your state? For state-specific strata information, take a look here.

Are you not sure about some of the strata terms used in this article? Take a look at our NSW Strata Glossary to help with your understanding.

After a free PDF of this article? Log into your existing LookUpStrata Account to download the printable file. Not a member? Simple – join for free on our Registration page.

Share with your strata community

  • Share
  • LinkedIn
  • Email

Comments

  1. Philip O'Sullivan says

    October 30, 2024 at 8:37 am

    We are a strata with 33 units in two buildings. We need to have the waterproofing membrane on both roofs replaced. The roofs are a flat concrete structure and the building was constructed in 1984

    In the scope of works prepared by the engineer they quote a $35,000 premium for the HBCF insurance certificate and $20,000 for the lodgement of documents with the DBPA.

    How can I check these quotes are reasonable. I am doubtful about the insurance quote given we have not yet gone to tender and thus do not have quotes for the repair costs.

    Reply
    • Liza Admin says

      June 16, 2025 at 6:36 am

      Hi Phillip

      Thank you for your comment. Bruce McKenzie, Sedgwick has responded to your queston in the article above.

      Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Search For Strata Articles

  • Advert Stratabox
  • StrataBox Advert
Subscribe Newsletter

TESTIMONIALS

"LookUpStrata should be compulsory reading for every member of a Body Corporate Committee. It provides the most understandable answers to all the common (and uncommon) questions that vex Body Corporates everywhere. Too often Committee members do not understand what Body Corporates are legally able to do and not do. LookUpStrata helps educate everybody living in a Body Corporate environment for free." John, Lot Owner

"It's the best and most professional body corporate information source a strata manager could have! Thanks to the whole team!" MQ, Strata Manager

"I like reading all the relevant articles on important issues on Strata living that the LookUpStrata Newsletter always effectively successfully covers"
Carole, Lot Owner

"Strata is so confusing and your newsletters and website are my go-to to get my questions answered. It has helped me out so many times and is a fabulous knowledge hub." Izzy, Lot Owner

Quick Login

Log In
Register Lost Password

Categories

  • Contact a Strata Specialist on the LookUpStrata Directory
  • Ask Us A Strata Question
  • New South Wales
  • Queensland
  • Victoria
  • Australian Capital Territory
  • South Australia
  • Tasmania
  • Western Australia
  • Northern Territory
  • ByLaws & Legislation
  • Smoking
  • Parking
  • Noise & Neighbours
  • Insurance
  • Pets
  • Levies
  • Law Reform
  • Maintenance & Common Property
  • Committee Concerns
  • NBN & Telecommunications
  • Building Defects
  • Renting / Selling / Buying
  • Strata Managers
  • Building Managers and Caretakers
  • Strata Reports / Plans
  • Sustainability

Recent Comments

  • Irene smith on QLD: Q&A Who Can Access Common Property?
  • Fris on QLD: Q&As Keys, fobs, swipe cards, security access and issues
  • Nikki Jovicic on VIC: Expert Panel To Review Owners Corporation Laws
  • Nikki Jovicic on QLD: Removing a terrible Caretaker – Terminating Management Rights. VIDEO
  • Josephine Tedesco on VIC: Expert Panel To Review Owners Corporation Laws
  • Auriel June on NAT: Understanding concrete cancer in strata buildings
  • Pauline Saunders on WA: Strata Manager Qualification Requirements Changes and Compliance
  • Barry Beveridge on QLD: Removing a terrible Caretaker – Terminating Management Rights. VIDEO
  • Barry Ewing on QLD: Owner Improvements
  • Josephine Tedesco on VIC: Expert Panel To Review Owners Corporation Laws

WEBSITE INFORMATION

  • Privacy Policy
  • Terms and Conditions of Use
  • Terms of Use for Comments and Community Discussion
  • Advertising Disclosure
  • Sitemap

ASK A STRATA QUESTION

You’ve Found Strata Help!

Ask a strata, owners corporation or body corporate question and we will do our best to source a useful response from our network of strata professionals around Australia. Submit your question here.

Disclaimer

The opinions and/or views expressed on the LookUpStrata site, including, but not limited to, our blogs and comments, represent the thoughts of individual bloggers and our online communities, and not those necessarily of LookUpStrata Pty Ltd. In all instances, information should not be taken as advice and independent legal advice should be consulted.

CONTACT US VIA EMAIL

Copyright © 2025 · LookUpStrata ® Pty Ltd · All rights reserved